Canadian Underground Infrastructure Logo

Huge Vancouver water main project enters final stretch

The 3.5-metre-diameter tunnel is approximately 30 metres below the river bed, and was constructed between two 60-metre-deep vertical shafts using a Caterpillar TBM named Squirrel. The TBM was lowered in February 2014 and removed on July 17.
The 3.5-metre-diameter tunnel is approximately 30 metres below the river bed, and was constructed between two 60-metre-deep vertical shafts using a Caterpillar TBM named Squirrel. The TBM was lowered in February 2014 and removed on July 17.

Depth, tight quarters keep workers on their toes

When a key water main was damaged by river scour – or high water flow resulting from snow and ice melt – in 1997, Metro Vancouver decided a new approach was needed.

The 40-year-old main, which links Coquitlam to Surrey and points beyond the Fraser River, was successfully repaired the following year, but the incident made it clear that the line would eventually have to be replaced.

Enter the new $240-million Port Mann Water Supply Tunnel, which more than doubles the existing main’s capacity and runs for one kilometre below the floor of the Fraser, starting at Maquabeak Park on the river’s north side, in Coquitlam, and terminating at the CN Thornton Yard in Surrey, on the south side.

The main contractor, a joint venture between Canadian contractors McNally International Inc. and Aecon Group Inc., broke ground on the project in 2011.

The tunnel, which measures 3.5 metres in diameter, was completed on July 17, when the tunnel boring machine (TBM), made by Caterpillar Tunnelling Canada Corp. and nicknamed Squirrel, was removed from a shaft on the river’s north side. Workers are now installing the 2.1-metre-diameter water main within the tunnel. Completion is slated for fall 2016, at which point the main will carry roughly a billion litres of water a day from Coquitlam to Surrey.

GOING DEEP

Infrastructure like this has a lifespan of up to 200 years, so engineers had to take a wide range of factors into account, such as the region’s projected long-term growth rate and above-average seismic activity, not to mention making sure the new main could withstand the Fraser’s force better than its predecessor.

Part of the answer was to go deep, says Murray Gant, lead senior engineer with the Major Projects Group in Water Services at Metro Vancouver.

“The tunnel’s about 30 metres below the bottom of the river, which is about 55 to 60 metres below the ground surface on both sides on the land side. There are sandy deposits on both banks of the river that could lose strength during a large earthquake and actually flow in toward the river, so that meant putting the tunnel deep to avoid that hazard.”

To protect the tunnel from the weight of the earth and water above, a crew followed the TBM along inside the tunnel, assembling and installing concrete rings as they went.

“As you mine through, how the sequence goes is you actually mine a metre – like you tunnel a metre – and then you install precast concrete segments in a ring that has these heavy duty rubber gaskets,” says Gant. “The rings are bolted and gasketed, and that provides the temporary support for the tunnel as it’s mined.”

TAKING A SWIM

The end of the tunnel drive is a major milestone for the project, whose first phase was the construction of two 60-metre-deep vertical shafts on each side of the river, necessary for launching and retrieving the TBM.

To dig them, workers employed a cranemounted Bauer hydromill to excavate vertical slots to the shafts’ full depth. They then backfilled those slots with concrete to create slurry walls, which provided temporary support while they excavated the shaft interiors using a Liebherr Model 855 clamshell bucket.

But working below the water table added an extra challenge: to maintain stability and keep material from coming in at the bottom, each shaft had to be kept full of water. To install the necessary base slab, divers had to be lowered in cages to attach rebar reinforcements before the concrete could be poured.

Once below the surface, the divers, employed by subcontractor Ballard Marine Construction of Seattle, worked in the muddy water with zero visibility for an hour at a time before being pulled back up. They then had to be moved to an on-site hyperbaric chamber within four minutes to avoid decompression sickness.

TBM: SOME ASSEMBLY REQUIRED

The vertical shafts also posed a challenge for the mining crew: after the final concrete linings were installed, each shaft’s inside diameter was just 11 metres – much too small for the 80-metre-long TBM.

The solution? Break it into pieces. “The tunnel boring machine has to basically function as if it’s fully under the river, but of course you don’t have any room in the shaft,” says Gant. “So they had all of these power cords and grout lines extending up this 60-metre-deep shaft to the surface.

“All of the equipment, the trailing gear for the tunnel boring machine, was at the surface, and then the tunnel boring machine had to start boring under the river. Once it got about 80 or 90 metres in, then of course all of the trailing gear could be added piece by piece.”

In all, the tunnelling took 16 months to complete, compared to a best-case estimate of three months, due to challenging ground conditions and a five-month delay when the TBM broke down with just 200 metres to go.

“The challenges both during shaft construction and tunnel construction related to the significant depth of soil deposits and the high groundwater table,” says Gant. “Initially the upper units were sandy and silty, but then we get down into a dense glacial till-type deposit, which contains cobbles and some boulders and so on.”

“So it just took extra time to excavate the shafts and construct the shafts, and then extra time tunnelling through the same kind of dense deposits.”

MORE CROSSINGS PLANNED

With the tunnelling behind them, the joint venture and its subcontractors are now focused on installing the 25-millimetre- thick steel main and completing the two valve chambers that will link it to the existing water system.

For its part, Metro Vancouver sees the Port Mann project as a major step in its ongoing upgrade to the area’s water system.

“We do have plans to build other tunnel crossings, both at the Fraser River and Burrard Inlet, to bring the whole system up to the seismic design standard, so we can deliver water after a major earthquake to the region,” says Gant. CUI

To facilitate the TBM drive and installation of a 2.1-metre-diameter welded steel water main, two shafts are being excavated on each side of the Fraser River. To dig them, workers employed a BC40/MC128 Hydromill provided by Bauer.

More from Water & Sewer Construction

Acrobat 315 meets pipe fusion capability needs

The new McElroy Acrobat 315 is helping meet the demand for larger polypropylene pipe fusion capability up to 315mm (12") while offering low- and high-force options for polyethylene pipe. The compact, lightweight machine caters to the HVAC, plumbing and mechanical industry as well as the underground/construction world. It functions as easily indoors in tight work spaces as it does outdoors in the smallest trenches. 

Miami Beach HDD installation recognized as Plastic Pipe Institute's Project of the Year

The longest horizontal directional drilled (HDD) installation of high-density polyethylene (HDPE) pipe in the United States and Canada was recognized as Project of the Year by the Plastics Pipe Institute, Inc. (PPI). The award was presented to PPI member company ISCO Industries at the association's annual membership meeting in May 2017. PPI is the major North American trade association representing all segments of the plastic pipe industry,

McLaughlin Adds New PTO-driven Options to MEGA VAC Line

The Vermeer MEGA VAC VXT truck series by McLaughlin is a highly productive vacuum excavator designed to meet increasingly strict weight restrictions and regulations. Ideal for utility and distribution contractors, the VXT Series is a reliable, cost-effective solution for high-production potholing crews. The new 6-inch (15.2 cm) PTO-driven series comes in three standard spoil capacities ranging from 1,200 to 2,000 gallons (4542.5 to 7570.8 L). The VXT series is powered by the industry-proven OMSI Gearbox and a ROOTS 3200 CFM (91 m3/min) blower. The new CAN Control system allows for two-way communication between the remote control and the vacuum excavator, which helps contractors increase jobsite productivity. The new Vacuum Neutral feature allows the blower to breathe free air and stop suction without the need to close the hydraulic gate valve in the boom.

McElroy’s Self-Propelled TracStar® 1200 for Thermoplastic Pipe Fusion

The McElroy TracStar 1200 fuses pipe from 16" OD to 48" OD (450mm to 1200mm) bringing the largest pipe fusion capability to its line of track-mounted machines. Upgrades include an advanced emission control engine that burns ultra-low-sulfur diesel to meet US EPA Tier 4/EU Stage IIIB standards and the ability to upload joint reports to the DataLogger® Vault™ for storage and analysis. A redesigned cowling and rearrangement of internal components allows better access to the engine for maintenance. Other features include hydraulic outriggers for machine stability and leveling, an ergonomic operator platform and remote engine stop/start capabilities. 

Con Cast Pipe acquires Hy-Grade Precast Concrete

Con Cast Pipe, a manufacturer of precast concrete drainage products including concrete pipe, manholes, catchbasins, and box units, as well as a wide range of bridge and specialty precast products in Canada, has announced the recent purchase of Hy-Grade Precast Concrete in St. Catharines, Ontario. Due to their outstanding reputation in the Niagara community, Hy-Grade Precast Concrete will continue to operate under the Hy-Grade name and become the third Ontario manufacturing facility for Con Cast Pipe.

Vac-Tron Equipment has developed a new gamechanger in the Micro Trenching process

Micro Trenching is one of the installation methods being utilized by contractors to bring fiber networks to consumers. Micro Trenching is an installation method in which a narrow and relatively shallow trench is cut, usually on an asphalt roadway. Trench dimensions can range from .75 to 2.24 inches wide and 8 to 16 inches deep. While cutting, a vacuum system connected to the cutter wheel cleanly diverts and transports debris away from the worksite. Once the conduit is laid, the trench is backfilled with a grout compound. Advantages of Micro Trenching include minimal cutting width that boosts installation production, reduce costs of backfill, shallow depth placement which helps avoid encounters with existing utilities and jobsite cleanliness thanks to the vacuum spoil that removes debris.

free-paper-airplane

Get our newsletter

Learn more

TT Technologies offers new cutterhead configuration for static pipe bursting operations

TT Technologies recently introduced a new cutterhead configuration for its Grundoburst static pipe bursting system. The new configuration consists of three specially designed bladed, roller cutterheads in succession. The bladed roller cutting head configuration allows contractors to burst/split large diameter steel and ductile iron pipes when used with larger Grundoburst static bursting systems. The new special cutterhead design allows for a smoother host pipe cut and greater protection for the new pipe.

Polyurethane grouts from Avanti now certified by WQA for use with potable water applications

Avanti International’s AV-248-LV Flexseal LV, AV-275 Soilgrout and AV-315 Microfoam are now certified by the Water Quality Association (WQA) as tested and certified against NSF/ANSI Standard 61 - Drinking Water System Components. Avanti’s products are used to stop leaks, stabilize soil, and control groundwater in municipal, industrial, and geotechnical applications. According to technical director Roger Borremans, “These three products join three other Avanti resins earning Potable Water Certification. Engineers now have more choices between hydrophilic and hydrophobic resins for specifying the exact right product in potable water applications.”

New Milton sewer tunnels through environmentally sensitive areas

The population growth of the Town of Milton, Ontario in recent years has been phenomenal. With the province’s Places to Grow legislation, this growth is expected to continue for many years. The Boyne Trunk Sanitary Sewer was identified in the Halton Region’s Wastewater Master Plan as being critical to convey existing and future flows to the Mid Halton Wastewater Treatment Plant in Oakville. The existing sewage pump station and force main conveying sewage from Milton was at its maximum capacity. The commissioning of a new major trunk sewer to replace the existing system and to convey future flows from the northern part of the region was of critical importance.

Finding the keys to Rebecca Trunk

In order to balance the needs of growing the Region of Halton with the protection and preservation of its natural and heritage resources, Halton initiated Sustainable Halton which developed goals that serve as a blueprint for building a sustainable and healthy community. The need to upgrade the existing wastewater network to service future intensification in Oakville’s Urban Growth Centre was identified as part of the process.

HOBAS NC line installed in Quebec

When an old storm water sewer that crossed below a highway and a highly frequented shopping avenue in the City of Quebec partly collapsed and had to be replaced, the city government was presented with a challenge. The solution required a method to renovate the pipeline while keeping traffic disruptions to a minimum.

free-magazine-subscription

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more

McLaughlin introduces ECO Series of truck mounted vacuum excavators for utility market

McLaughlin has introduced the new ECO truck-mounted vacuum excavator series to answer the market’s demand for a compact vacuum excavation system that focuses on performance and improved fuel efficiency. Powered by 49, 85 or 99 horsepower (37, 63 or 74 kW) auxiliary engines, ECO Series vacuum excavators offer utility contractors fuel economy, lower operating costs and reduced maintenance. With the ability to choose from 500- to 1200-gallon (1892.7 to 3028.3 L) spoil tank capacities ― and the ability to mount ECO Series units on both new and used truck chassis ― contractors can customize the truck vacuum excavator to their specific needs.

Geopolymers 101: Ease of application, resistance to corrosion and light environmental footprint among advantages compared to competing spray technologies and CIPP

Geopolymer is a term originally coined by French researcher Joseph Davidovits to describe a class of “cement” formed from aluminosilicates. While traditional Portland cement relies on the hydration of calcium silicates, geopolymers form by the condensation of aluminosilicates. Geopolymers are known to provide comparable or better performance to traditional cementitious binders but with the added advantages of significantly reduced greenhouse emissions, increased fire and chemical resistance, and reduced water utilization.

Dealing with root causes

On Eastlawn Street in the City of Windsor, Ontario, heritage homes on double lots with mature trees beautifully line the narrow street. Not so beautifully, white sewer access caps dot the lawns of more than half of the homeowners. It is a telling sign of the ongoing battle between concerned homeowners and the roots they cannot see underground.

A tale of two manhole fixes

Canadian contractors are cost effectively rehabilitating failing manholes and sewers without excavation or barrel replacement using the Permacast and CentriPipe systems developed by AP/M Permaform (AP/M) and distributed by Martech, Inc. Edmonton-based OSCO Mudjacking & Shotcreting Ltd. applied Permacast on two manhole projects with widely varying challenges:

  • A new 9-metre manhole installed as part of Edmonton’s massive project converting the QE II Highway and 41 Avenue SW connection to a grade-separated interchange.
  • Six failing manholes in remote Carmacks, a Yukon village.
free-paper-airplane

Get our newsletter

Learn more

Trimble launches new version of its smart water management software to streamline utility field operations

Trimble has announced the latest version of its smart water mapping and work management software—Trimble Unity 3.0. Trimble Unity is a cloud-based, (GIS) centric software-as-a-service (SaaS) solution for smart water management. Version 3.0 includes new features and workflows and also offers an App Builder and new integration capabilities to simplify connecting mobile workers with maps and data from back office enterprise systems.

Use vacuum excavation for safe digging

April is National Safe Digging month and every year many companies, including 811 and Click Before You Dig, promote the importance of having a plan before you begin digging. Every six minutes an underground utility line is damaged and the growing trend in preventing these accidents is utilizing vacuum excavation. There are many instances when vacuum excavation is the safest and most productive option for digging compared to traditional excavation.

Tips for keeping your vacuum excavator in peak winter condition

When cold weather conditions set in, regular maintenance and a heightened awareness of how to keep vacuum excavation equipment operating properly is required to avoid costly repair expenses. In the oil and gas market alone, there are thousands of vacuum excavators at work in oil fields across North America, and a majority of these units are working through the winter in extremely cold conditions.

European Dryvacs rolling into North America

Often seen as the workhorse of the underground construction industry, the hydro-vacuum truck is almost ubiquitous in its presence on most jobs involving the removal of dirt and debris from underground utilities. Whether it’s potholing to expose buried facilities, sucking up drilling fluid during an HDD project, or custom-fitting a hydrovac truck to perform sewer cleaning operations, the diversity of applications available to a hydrovac make it an indispensable piece of equipment for a utility contractor to own or rent.

Toro introduces the Pro Sneak 365 vibratory plow

The Toro Pro Sneak 365 Vibratory Plow delivers powerful plowing in a compact, maneuverable package perfect for installing drip irrigation lines, electrical cable or other utilities in tight spaces. Utility contractors appreciate the narrow tire configuration of the Pro Sneak, which spans 36” in width, allowing for passage through gates, or other obstacles. Also available on the new Pro Sneak 365 is the dual-tire option for increased traction in challenging ground conditions.

Ultrafine from US Grout and Avanti - cementitious grout certified by NSF for potable water use

2015 was a game changer for the grouting industry, US Grout, LLC and Avanti International. As of this year, US Grout's Ultrafine SD and Ultrafine ND Cementitious Grouts - solely distributed by Avanti - are now certified by NSF International as conforming to the requirements of NSF/ANSI Standard 61 - Drinking Water System Components - Health Effects. In other words, Ultrafine SD and ND are certified for use in contact with potable water. Since the early 1940s, NSF International has developed standards, tests and certified products and systems to protect and improve global human health. For engineers and contractors, this is a differentiator.

Waterloo biofilm battle

In Canada, the quality of drinking water that flows from the taps of most households is for the most part taken for granted. While the country has pockets of populations with water quality concerns, Canadians generally regard their drinking water not only as safe, but of a higher quality than other developed nations.

free-magazine-subscription

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more