Canadian Underground Infrastructure Logo

Huge Vancouver water main project enters final stretch

The 3.5-metre-diameter tunnel is approximately 30 metres below the river bed, and was constructed between two 60-metre-deep vertical shafts using a Caterpillar TBM named Squirrel. The TBM was lowered in February 2014 and removed on July 17.
The 3.5-metre-diameter tunnel is approximately 30 metres below the river bed, and was constructed between two 60-metre-deep vertical shafts using a Caterpillar TBM named Squirrel. The TBM was lowered in February 2014 and removed on July 17.

Depth, tight quarters keep workers on their toes

When a key water main was damaged by river scour – or high water flow resulting from snow and ice melt – in 1997, Metro Vancouver decided a new approach was needed.

The 40-year-old main, which links Coquitlam to Surrey and points beyond the Fraser River, was successfully repaired the following year, but the incident made it clear that the line would eventually have to be replaced.

Enter the new $240-million Port Mann Water Supply Tunnel, which more than doubles the existing main’s capacity and runs for one kilometre below the floor of the Fraser, starting at Maquabeak Park on the river’s north side, in Coquitlam, and terminating at the CN Thornton Yard in Surrey, on the south side.

The main contractor, a joint venture between Canadian contractors McNally International Inc. and Aecon Group Inc., broke ground on the project in 2011.

The tunnel, which measures 3.5 metres in diameter, was completed on July 17, when the tunnel boring machine (TBM), made by Caterpillar Tunnelling Canada Corp. and nicknamed Squirrel, was removed from a shaft on the river’s north side. Workers are now installing the 2.1-metre-diameter water main within the tunnel. Completion is slated for fall 2016, at which point the main will carry roughly a billion litres of water a day from Coquitlam to Surrey.

GOING DEEP

Infrastructure like this has a lifespan of up to 200 years, so engineers had to take a wide range of factors into account, such as the region’s projected long-term growth rate and above-average seismic activity, not to mention making sure the new main could withstand the Fraser’s force better than its predecessor.

Part of the answer was to go deep, says Murray Gant, lead senior engineer with the Major Projects Group in Water Services at Metro Vancouver.

“The tunnel’s about 30 metres below the bottom of the river, which is about 55 to 60 metres below the ground surface on both sides on the land side. There are sandy deposits on both banks of the river that could lose strength during a large earthquake and actually flow in toward the river, so that meant putting the tunnel deep to avoid that hazard.”

To protect the tunnel from the weight of the earth and water above, a crew followed the TBM along inside the tunnel, assembling and installing concrete rings as they went.

“As you mine through, how the sequence goes is you actually mine a metre – like you tunnel a metre – and then you install precast concrete segments in a ring that has these heavy duty rubber gaskets,” says Gant. “The rings are bolted and gasketed, and that provides the temporary support for the tunnel as it’s mined.”

TAKING A SWIM

The end of the tunnel drive is a major milestone for the project, whose first phase was the construction of two 60-metre-deep vertical shafts on each side of the river, necessary for launching and retrieving the TBM.

To dig them, workers employed a cranemounted Bauer hydromill to excavate vertical slots to the shafts’ full depth. They then backfilled those slots with concrete to create slurry walls, which provided temporary support while they excavated the shaft interiors using a Liebherr Model 855 clamshell bucket.

But working below the water table added an extra challenge: to maintain stability and keep material from coming in at the bottom, each shaft had to be kept full of water. To install the necessary base slab, divers had to be lowered in cages to attach rebar reinforcements before the concrete could be poured.

Once below the surface, the divers, employed by subcontractor Ballard Marine Construction of Seattle, worked in the muddy water with zero visibility for an hour at a time before being pulled back up. They then had to be moved to an on-site hyperbaric chamber within four minutes to avoid decompression sickness.

TBM: SOME ASSEMBLY REQUIRED

The vertical shafts also posed a challenge for the mining crew: after the final concrete linings were installed, each shaft’s inside diameter was just 11 metres – much too small for the 80-metre-long TBM.

The solution? Break it into pieces. “The tunnel boring machine has to basically function as if it’s fully under the river, but of course you don’t have any room in the shaft,” says Gant. “So they had all of these power cords and grout lines extending up this 60-metre-deep shaft to the surface.

“All of the equipment, the trailing gear for the tunnel boring machine, was at the surface, and then the tunnel boring machine had to start boring under the river. Once it got about 80 or 90 metres in, then of course all of the trailing gear could be added piece by piece.”

In all, the tunnelling took 16 months to complete, compared to a best-case estimate of three months, due to challenging ground conditions and a five-month delay when the TBM broke down with just 200 metres to go.

“The challenges both during shaft construction and tunnel construction related to the significant depth of soil deposits and the high groundwater table,” says Gant. “Initially the upper units were sandy and silty, but then we get down into a dense glacial till-type deposit, which contains cobbles and some boulders and so on.”

“So it just took extra time to excavate the shafts and construct the shafts, and then extra time tunnelling through the same kind of dense deposits.”

MORE CROSSINGS PLANNED

With the tunnelling behind them, the joint venture and its subcontractors are now focused on installing the 25-millimetre- thick steel main and completing the two valve chambers that will link it to the existing water system.

For its part, Metro Vancouver sees the Port Mann project as a major step in its ongoing upgrade to the area’s water system.

“We do have plans to build other tunnel crossings, both at the Fraser River and Burrard Inlet, to bring the whole system up to the seismic design standard, so we can deliver water after a major earthquake to the region,” says Gant. CUI

To facilitate the TBM drive and installation of a 2.1-metre-diameter welded steel water main, two shafts are being excavated on each side of the Fraser River. To dig them, workers employed a BC40/MC128 Hydromill provided by Bauer.

Related Articles

Sponsored Brought to you by: Bobcat Company Logo

THE BOBCAT E88: STRENGTH IS ON YOUR SIDE

As one of the latest models in the R2-Series excavator lineup, the Bobcat® E88 delivers durability, performance and quality for more productivity. Technically speaking, it's a compact machine, but it brings big performance with its redesigned engine and optimized lift performance, plus undercarriage and counterweight improvements. All these enhancements make this excavator one of the highest-performing models in its size class. With impressive over-the-side lift capacity, you can dig with greater confidence over the side of the machine. Put it to the test against similar models from other manufacturers. You'll see that the E88 can outwork the competition.

Learn more