Canadian Underground Infrastructure Logo

Robbins achieves another breakthrough in Bangalore

Robbins drives two competitor EPB machines to a milestone at Namma Metro

EPB Kaveri in the launch pit at Chickpet in March 2015
EPB Kaveri in the launch pit at Chickpet in March 2015

Company info

29100 Hall Street
Solon, OH
US, 44139

Website:
therobbinscompany.com

Read more

On June 8, 2016, one of two 6.4 m (21.0 ft) diameter mixed-face EPB machines broke through at Namma Metro. After being launched in March 2015, the TBM named Kaveri made its way through its difficult 750 meter (2,460 ft.) drive from Chickpet to Majestic. Sister machine Krishna, launched in December 2015 is not far behind, and is expected to break through in approximately two months.

In February 2015, Robbins, with its operating company Robbins India, was asked by Bangalore Metro Rail Corporation Limited to take over the operation and maintenance of two competitor-owned EPBMs. The machines were stalled due to low performance and financial issues from the Operating Contractor and lack of support by the original machine supplier. As the North-South Bangalore Phase 1 Metro tunnels were on the critical path, the BMRC looked to Robbins to step in and take over the troubled project. A Robbins/Robbins India team of 70 field service personnel refurbished and modified the existing equipment, both while in the tunnel and before relaunching the machines in Chikpet station. In addition, the on-site Robbins/Robbins India Team supervised all aspects of TBM excavation, segmental lining, mucking and grout plant operations since the relaunch of the machines for both drives.

“I am particularly proud of being involved in this project, and to support BMRC with the completion of this tunnel drive and bringing the project back on schedule. This is also the first time The Robbins Company has been responsible for the complete scope of operations on a project,” noted Jim Clark, Projects Manager with Robbins India. “One of the biggest challenges we faced was carrying out cutterhead interventions under compressed air in mixed ground conditions that consisted of varying grades of granite in the lower half of the face, and loose, unconsolidated material in the upper section of the face.”

Clark said that on numerous occasions, compressed air would percolate through to the surface, forcing crews to abort cutterhead interventions. They eventually found a solution by pumping a weak mix grout though the mixing chamber, and into the geology surrounding the tunnel face. The weak mix grout stabilized the ground sufficiently so the cutterhead interventions could be completed.

The Robbins crew carried out tunneling operations while the station was being constructed around them to mitigate delays incurred before they took over project operations. The project’s most difficult challenges included a low overburden and consolidated ground along the alignment, and the discovery of several uncharted wells directly on the alignment. In addition, the majority of the tunnel was bored directly beneath buildings constructed upon what is today considered substandard foundations.

This portion of the Phase One Metro tunnels runs from Chickpet to Majestic at Namma Metro. Once Krishna breaks through, the North and South runs of Bengaluru will be connected, allowing service to an average of 40,000 passengers daily. It is being completed under a tripartite agreement between Robbins India, Coastal Projects Limited, the lead contractor, and project owner, Bangalore Metro Rail Corporation Limited. It is anticipated Phase One will be open in its entirety by November, 2016.

Robbins and crews celebrate Kaveri’s breakthrough on June 8 at Majestic after a 750 m (2,640 ft.) drive.
One of two 6.4 m (21.0 ft) diameter mixed-face EPB used to excavate from Chickpet to Majestic.
Lok Home, Robbins CEO, joins the Robbins India team in celebrating Kaveri’s breakthrough at Majestic on June 8, 2016.
(Left to Right) Lok Home, Robbins CEO, with BMRC Chief Engineer S.S. Hegaraddi. Robbins India Projects Manager Jim Clark, and Robbins India Managing Director Kapil Bhati.

More from Projects

Sanexen successfully finishes NYC tunnel repairs in record time

During the weekend of October 20th, Sanexen Water, Inc., a member of the LOGISTEC family, successfully completed major repairs in the Lincoln Tunnel in New York City with minimal impact. When the Port Authority of New York and New Jersey (PANYNJ) began planning repairs and upgrades to Route 495 and the Lincoln Tunnel, one of the requirements was to repair two cast iron cement-encased water main sections at each end of the tunnel that supply water for fire prevention.  Sanexen Water was selected for its unparalleled expertise and its innovative Aqua-Pipe trenchless technology, to repair these aging water mains while other construction work was in progress. New trenchless technology is used for the replacement or rehabilitation of existing underground infrastructure with minimal excavation and disruption to surface traffic. 

Final double breakthrough at the Emscher sewer

With the breakthrough of the last two tunnel boring machines into the target pit in Oberhausen-Biefang on June 12, 2017 the tunnel and pipe jacking work for the Emscher sewer has been completed. Over a period of 25 years numerous Herrenknecht tunnelling machines and a wide range of additional equipment were successfully used in the Europe-wide unique environmental and sewage project of Emschergenossenschaft.

Bulls Bridge Replacement Penstock

In the early 1900s, the New Milford Power Company successfully completed the first commercially viable hydroelectric power plant on the Housatonic River in Connecticut.  The project, Bulls Bridge Development, broke ground in spring 1902 and was in operation by 1903. Bulls Bridge was named after the Bull family that had lived in the area for generations. 

Herrenknecht tunnel borers continue success story in L.A.

Los Angeles is a vibrant center of international film art and innovation - not just on the surface. The area below ground is the scene of state-of-the-art engineering achievements. German high-tech machines from Herrenknecht are creating underground arteries for the American city. Tunnel boring machine (TBM) , Harriet successfully completed her drive for the Crenshaw/LAX Transit Project in April 2017. Angeli just finished digging the first of two tunnels for the Regional Connector Transit Corridor on July 18th. From spring 2018 onward the tunnel boring stars will have additional company: for each of the "Purple Line Extension Sections 1 + 2", two more Herrenknecht TBMs will be working their way through the difficult ground. All three projects are part of the strategic subway extension in L.A. to relieve the traffic above ground.

Mexico City’s Record-Breaking Crossover TBM makes Final Breakthrough

In June , a select group of project officials, including Mexico's President Enrique Peña Nieto, celebrated the final breakthrough of an epic tunneling project.  The 8.7 m (28.5 ft) diameter Robbins Crossover TBM is the first such hybrid machine to operate in North America, and it completed the Túnel Emisor Poniente (TEP) II on a high note.  The TBM, known an XRE—a Crossover (X) between Rock (R) and EPB (E) TBMs—navigated fault zones, variable ground, low cover, and more to achieve a national record of 57 m (187 ft) in one day as well as maximum rates of 231 m (758 ft) in one week and 702 m (2,303 ft) in one month. 

Speedy pipeline connection in Australia

In just three months Australian drilling contractor Dunstans Construction Group installed a 700-meter-long pipeline in Anglesea (Victoria). A 250 tonne HDD Rig from Herrenknecht played a key role in the achievement. Within a very short time the construction crew built a sea outfall with the machine, as well as pulling in the pipeline all the way back to the local water treatment plant.

Worksite injuries driving demand for composite manhole covers

Composite materials are in demand as industries are experiencing hazards and injuries when using traditional steel and other metal products. Reports of crushed and amputated fingers and toes along with burns, back injuries and other ailments have given industries ranging from data centres to water treatment plants a reason to seek safer alternatives. In the United States in 2014-15 there were 3,675 incidences of reported injuries within the manufacturing industry alone. Thirty-two percent of these incidences were reported as back injuries which led to a total of 125,880 missed working days. Composites are an ideal solution to these problems due to their lightweight yet durable properties. By using lighter materials, operational injuries are prevented, worksites are made safer, and ease of installation and maintenance is made available to utility workers and contractors.

Montreal-based consultancy completes inspection and leak detection of six 1,200-mm steel watermains and one 1,500-mm PCCP main in Montreal

Since September 2013, GAME Consultants has been paving the way for the next generation of watermain condition assessment tools by using existing tools and working to improve the results with every project. The company’s position is to equip itself with a wide range of tools designed exclusively for use in watermains.

free-paper-airplane

Get our newsletter

Learn more

A tale of two manhole fixes

Canadian contractors are cost effectively rehabilitating failing manholes and sewers without excavation or barrel replacement using the Permacast and CentriPipe systems developed by AP/M Permaform (AP/M) and distributed by Martech, Inc. Edmonton-based OSCO Mudjacking & Shotcreting Ltd. applied Permacast on two manhole projects with widely varying challenges:

  • A new 9-metre manhole installed as part of Edmonton’s massive project converting the QE II Highway and 41 Avenue SW connection to a grade-separated interchange.
  • Six failing manholes in remote Carmacks, a Yukon village.

Completion of trackwork for the Toronto-York Spadina Subway extension

A special event was held to celebrate the completion of trackwork in the new Toronto-York Spadina Subway Extension (TYSSE) tunnels and stations where a total of 17.4 kilometres of track and four sections of special track have been installed. Dignitaries walked down into the station to track level where they participated in a ceremonial tapping in of the last clips that hold the rails in place.

Pipe change at Prince Edward Island watermain expansion project

As a PVC-friendly city, Summerside, Prince Edward Island planned to use PVC pipe as it began Phase II of its Pope Road watermain expansion project. The project required 300 metres of 400-mm (16-inch) pipe, and was taking place in an area of the city with no existing water line.

Waterloo biofilm battle

In Canada, the quality of drinking water that flows from the taps of most households is for the most part taken for granted. While the country has pockets of populations with water quality concerns, Canadians generally regard their drinking water not only as safe, but of a higher quality than other developed nations.

Innovative approach to sanitary sewer cleaning

Civil engineers could be looking at London as a template for hard-to-access sewer cleaning jobs. The Ontario municipality recently installed three specialized manholes with sealed access flanges into one of its longest and oldest sewers in order to clean the pipe, after a camera probe two years ago identified it as being partially filled with solids and grit that would eventually restrict flows.

Turbidity problem addressed

In Dieppe, New Brunswick, complaints about the quality of drinking water running through a decades-old water main had city engineers scratching their heads for a solution that wouldn’t create too much disruption for residents.

Robbins EPB Begins Light Rail Link

Tucked away on a small jobsite in a quiet neighbourhood bordering a busy interstate highway, a Robbins Earth Pressure Balance (EPB) machine underwent Onsite First Time Assembly (OFTA). The OFTA method allows for TBMs to be assembled onsite, and results in time and cost savings to the contractor. On November 17, 2014 unbeknownst to commuters driving by, the 6.65-metre (21.8 feet) TBM rumbled to life and began its journey south into the city of Seattle, Washington.

Concrete Conduit Challenges Pipe-Bursting Contractor

One of the most effective ways of replacing a pipe using trenchless technology is pipe bursting, which replaces a traditional construction trench with launching and receiving pits that pull the new pipe through the existing one, breaking the old pipe into fragments that stay in the ground in-situ.

free-magazine-subscription

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more

Tendering the Environment

Environmental concerns and mishaps have been the cause of many delays, cost overruns, shutdowns and legal implications over the years. Many people in the industry will read this and think that delays caused by environmental factors are a result of multiple, complicated or changing regulations. While these are sometimes contributing factors, the root of the problem starts with contract tenders, more specifically the way they are written or not written.

Breaking Through to Billy Bishop

It is only 120 metres across the Western Gap of Toronto Harbour from the Toronto waterfront to the Billy Bishop Toronto City Airport (BBTCA) but it still requires a ferry boat ride for passengers going to and returning from the airport on Toronto Island. The ever-increasing popularity of this airport with close proximity to downtown Toronto has pushed the ferry capacity to its limits.

CUC crews endure extreme conditions to complete Air Liquide project

Working in underground construction, it’s common for utility contractors to encounter unexpected challenges. In fact, it’s those challenges that often test a company’s mettle, its expertise and its people. A successful outcome not only brings a sense of pride to those who were involved in the project, but can often cement a relationship with a customer that is both long-lasting and fruitful.

Revitalizing Toronto’s waterfront roads

Downtown Toronto benefits greatly from the natural beauty of Lake Ontario providing it with a stunning waterfront that attracts tourists and local residents on a daily basis. Combining traffic, transit, tourists and other factors in an area that was designed and developed many years ago has caused a call for revitalization along parts of the city’s waterfront.