Canadian Underground Infrastructure Logo

Robbins TBM rises to geological challenges in France

Galerie des Janots Main Beam completes Arduous French Drive

Contractor Eiffage Civil Construction celebrates the April 2019 breakthrough of a 3.5 m (11.5 ft) diameter Robbins Main Beam TBM in Cassis, France.
Contractor Eiffage Civil Construction celebrates the April 2019 breakthrough of a 3.5 m (11.5 ft) diameter Robbins Main Beam TBM in Cassis, France.

In April 2019, a Robbins 3.5-m (11.5-foot) diameter Main Beam TBM broke through into open space, completing its 2.8 km (1.7 mi) long tunnel. It was not the first time the machine had encountered open space: twice during tunnelling, the machine hit uncharted caverns, the largest of which measured a staggering 8,000 cubic metres (283,000 cubic feet) in size.  

The obstacles overcome at the recent breakthrough are a significant achievement, said Marc Dhiersat, Project Director of the Galerie des Janots tunnel for contractor Eiffage Civil Construction. "We are proud to have led a motivated and conscientious team to the end of the tunnel who worked well without accidents despite the many technical difficulties encountered." 

The water tunnel, located below the community of Cassis, France, is an area of limestone known for its groundwater, karstic cavities and voids. The limestone, combined with powdery clays, made for difficult excavation after the machine's March 2017 launch.  At the 1,035-m (3,395-foot) mark, the crew hit a cavern on the TBM's left side. The cavern, studded with stalactites and stalagmites, was grazed by the TBM shield.  

The crew had to erect a 4-m (13-foot) high wall of concrete so the TBM would have something to grip against. The TBM was then started up and was able to successfully navigate out of the cavern in eight strokes without significant downtime to the operation – the process took about two weeks. Despite the challenges, Dhiersat thought positively of the TBM throughout the ordeal: "This has been the best machine for the job due to all the geological difficulties."

Despite challenges including karstic limestone and clay, the Robbins TBM at Galerie des Janots achieved rates of 18 m (59 ft) per day on average, and topped out at 25 m (82 ft) in one day.

The first cavern, while the largest, was not the most difficult void encountered. The machine was averaging 20 to 22 m (65 to 72 feet) advance per day in two shifts after clearing the first cavity, with a dedicated night shift for maintenance. While excavating, a combination of probe drilling and geotechnical BEAM investigation – a type of electricity-induced polarization to detect anomalies ahead of the TBM – were used. Crews ran the excavation five days per week, achieving over 400 m (1,310 feet) in one month. 

This performance continued until the 2,157-m (7,077-foot) mark, when the machine grazed the top of an unknown cavity that extended deep below the tunnel path. The structure measured 22 m (72 feet) long, 15 m (49 feet) wide, and 14 m (46 feet) deep, or about 4,500 cubic metres (159,000 cubic feet) of open space.

The Robbins machine overcame tough conditions including two uncharted caverns, the largest of which measured a staggering 8,000 cubic meters (283,000 cubic ft) in size.

Crews probed in front of the cutterhead and began work to stabilize and secure the cavity with foam and concrete, as well as excavate a bypass gallery. "After filling much of the cavity (1,500 cubic metres/53,000 cubic feet), our biggest difficulty was to ensure the gripping of the machine: we needed six bypass galleries and four months of work to reach the end of this challenge," said Dhiersat. For the last 600 m (2,000 feet) of tunneling, "we were finally in good rock," he emphasized. Overall rates for the project averaged 18 m (59 feet) per day in two shifts, and topped out at 25 m (82 feet) in one day. 

"The cooperation with Marc and his team on site was very good and we always enjoyed their professionalism and commitment to the project and the task. This, without any doubt was key for the success we achieved," said Detlef Jordan, business manager Robbins Europe. 

"For us, it was satisfying and motivating to see that, by working together and joining the efforts of all partners on the project, the best and most successful outcome can be achieved. This commitment for decades has been at the heart of success in the tunneling industry, but it has not always been observed on other recent projects."

The first cavern, encountered at the 1,035 m (3,395 ft) mark, was grazed by the TBM shield on one side and was studded with stalactites and stalagmites.

Galerie des Janots is one of 14 operations designed to save water and protect resources, which are being carried out by the Aix-Marseille-Provence metropolis, the water agency Rhône Mediterranean Corsica, and the State Government. The Janots gallery, once online, will replace existing pipelines currently located in a railway tunnel – these original pipes have significant deficiencies with estimated water losses of 500,000 cubic metres (132 million gallons) per year. The new tunnel will increase capacity to 440 litres (116 gallons) per second.

The Robbins Main Beam TBM was launched to bore the Galerie des Janots, a new water tunnel, in March 2017.

The News In Brief: 

  • A Robbins 3.5-m (11.5-foot) diameter Main Beam TBM broke through in April 2019, completing a 2.8 km (1.7 mi) long tunnel in Cassis, France.
  • The Robbins machine overcame tough conditions including two uncharted caverns, the largest of which measured a staggering 8,000 cubic metres (283,000 cubic feet) in size.  
  • The Galerie des Janots water tunnel is an area of limestone known for its groundwater, karstic cavities and voids.  
  • Contractor Eiffage Civil Construction was able to advance through the caverns by erecting bypass galleries. In the case of the second cavern, this required six bypass galleries and four months of work.
  • Despite the challenges overall production rates with the Robbins TBM averaged 18 m (59 feet) per day in two shifts, and topped out at 25 m (82 feet) in one day. 
  • The Janots gallery, once online, will replace existing deficient water pipelines currently located in a railway tunnel, and increase capacity to 440 litres (116 gallons) per second.

Company info

29100 Hall Street
Solon, OH
US, 44139

Website:
therobbinscompany.com

Read more
Subscribe to our free newsletter

Get our newsletter

Learn more
Subscribe to our free magazine

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more
Subscribe to our free newsletter

Get our newsletter

Learn more
Subscribe to our free magazine

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more